Scheme Summary

The Green Futures housing project consists of 27 environmentally friendly houses developed by Black Country Housing Group, in partnership with Dudley Metropolitan Borough Council.


Scheme Details

The Green Futures housing scheme began in 1997. Phase 1, completed 1998, has been occupied for two years. Phases 2a and b were completed 2000. The final phase is under construction (Feb 2001).

Each phase has used a different construction technique, but all sought to show that homes can be designed and built to provide affordable and desirable housing, reduce negative environmental impact, make energy savings and use materials from sustainable sources.


Environmental Features

The houses are mainly two storey terraced. The following features are common to all phases.

Houses have generally been orientated to maximise solar gain. Site characteristics and the need to maintain privacy have affected orientation. Sun pipes provide natural daylighting to unlit areas, e.g. stairwells.

Materials were sourced locally, where possible. Bricks were made in the Black Country. Timber and particle board, although not sourced locally, were sourced in the UK.

Plastics were used sparingly where economic alternatives were unavailable. Recycled plastic was used for the external doors to Phase 2 properties.

The homes were designed to be energy efficient with thermal insulation helping to reduce the amount of space heating required. This was achieved through:

  • Draught lobbies front and rear of the homes (prevent warm air escaping when outside doors are opened).
  • 300mm of roof and wall insulation.
  • 100mm of basement insulation.
  • Low emissivity argon filled double glazed timber frame windows.

Fresh air is provided by mechanical ventilation with heat recovery, or passive stack ventilation. Each construction phase is summarised below.

Phase 1
15 houses were built using a conventional brick and block construction method. The cavity is wholly filled with 100mm of mineral wool insulation and reduces the amount of heat lost through the building fabric. The resulting U value is 50% better than the Building Regulations of the time.

Phase 2a
Phase 2 explored alternative construction techniques to improve insulation and energy efficiency. The four houses in phase 2a developed a hybrid construction method, increasing insulation levels whilst retaining some thermal mass. The cross walls at the end of each house are constructed with masonry. This provides thermal mass and improves fire and noise insulation and security. The front and rear walls are lightweight highly insulated prefabricated timber framed. The houses are quicker to erect and achieve higher levels of insulation than phase 1. 150mm of wall insulation improves energy efficiency by one third.

Phase 2b
Two houses were constructed of a proprietary system: Panablock. The system is a good thermal insulator and allows easy construction; two trained staff can erect an enclosed shell within a week (ready for finishing trades). The system achieves a U value of 0.29Wm2C. An additional 150mm of insulation was added to the cavity around the Panablock structure to improve the U value by 50%. Due to the restricted nature of this part of the site, three storey houses were built providing well insulated rooms in the roof. Roof insulation is 300mm - twice that required by Building Regulations.

Phase 2c
Six steel framed houses are due for completion in 2001.

All houses in Phase 2 include rainwater harvesting and grey water recycling systems. Composting toilets are installed in one house and an Eco-Pod training centre.


Thermal Efficiency

Despite the heat demand from Phase 1 houses being low, a traditional gas fired central heating system is installed. A comprehensive control system manages the heating effectively. Typically, weekly heating bills in Phase 1 have been halved to £4 compared with a regional average of £8 for a three bed house. With the improved thermal efficiency of Phase 2 houses, under floor heat systems connected to communal heat sources are used as follows:

  • Gas fired combined heat and power combustion engine - more than 90% efficient.
  • A ground source heat pump takes heat from the ground, where the temperature is a constant 24°C. Every 1kW of electricity used produces 3kW of heat.
  • Two high efficiency gas-fired condensing type boilers.
  • A low temperature hot water store provides a buffer between the various heat sources and heating systems.

Together the systems can deliver water at 60°C. In addition, 4m2 'flat-plate' solar water heaters have been fitted to some roofs. It is expected that these will save about 50% of the hot water fuel bill. Phase 2 heating bills are predicted to be as low as £2 a week.


Costs

The total scheme will cost £2million. Dudley Metropolitan Council donated the land and the scheme has been part funded by the European Regional Development Fund. The nature of the scheme and the inclusion of a training facility prevent a unit cost from being included.


Developer's Comments

This project is exploratory and provides a valuable demonstration of a range of techniques aimed to reduce environmental impact. The availability of a venue where sustainability can be witnessed first hand and in action will be of value to all social housing stakeholders.